Chapter 6 of 8

Chapter 6: Statistical Process Control (SPC)

6.1 Introduction

Up to this point, metrology in MET 135 has focused on measuring individual parts and evaluating instruments. In modern manufacturing, quality is rarely judged one part at a time. Instead, engineers monitor process behavior over time to prevent defects before they occur. This approach is known as Statistical Process Control (SPC).

SPC uses statistical tools and control charts to distinguish between normal process variation and abnormal variation that signals a problem. This chapter introduces run charts, X-bar charts, R charts, and decision rules used to determine whether a process is in control or out of control.

6.2 Why SPC Is Used in Manufacturing

SPC is a predictive quality tool. Unlike confidence intervals, which are applied after parts are produced, SPC identifies problems before parts go out of specification.

SPC allows manufacturers to:

In industry, SPC is a core requirement for quality systems such as ISO 9001 and Six Sigma.

6.3 Common Cause vs. Special Cause Variation

Common Cause Variation

Common cause variation is the natural, random variability inherent in a stable process.

Characteristics:

Examples:

A process with only common cause variation is considered stable and predictable.

Special Cause Variation

Special cause variation occurs when something unusual or assignable affects the process.

Characteristics:

Examples:

Special cause variation means the process is out of control and requires investigation.

6.4 Run Charts

A run chart plots measurement values over time without control limits. It is often the first step in SPC.

Run charts are used to:

Run charts do not determine control status by themselves.

6.5 Control Charts

Control charts add statistically calculated limits to distinguish normal variation from abnormal variation.

Key elements:

Control limits are not specification limits. They describe process behavior, not customer requirements.

6.6 X-Bar and R Charts

SPC in MET 135 uses X-bar and R charts for variables data.

X-Bar Chart

R Chart

Both charts must be in control for the process to be considered stable.

6.7 Calculating Control Limits

For a subgroup size n, control limits are calculated as:

X-Bar Chart:

UCLx̄ = x̄̅ + A₂·R̄
LCLx̄ = x̄̅ − A₂·R̄

R Chart:

UCLR = D₄·R̄
LCLR = D₃·R̄

Constants A₂, D₃, and D₄ depend on subgroup size and are obtained from standard tables (see the SPC constants table in Appendix A).

X-bar control chart showing common cause and special cause variation An X-bar control chart of shaft diameter subgroup averages in inches for 20 subgroups. A solid center line sits at 0.500 inches with dashed upper and lower control limits at 0.506 and 0.494 inches. Most points vary randomly close to the center line — labeled common cause variation. One point at subgroup 14 rises above the upper control limit and is circled — labeled special cause variation, requiring investigation. UCL LCL CL 0.506 0.500 0.494 Common cause variation (random, within limits) Special cause variation — investigate Subgroup number (shaft diameter averages, in)
Figure 6.1. An X-bar chart for a machining process. Random variation within the control limits is common cause; the circled point above the UCL signals special cause variation. (This figure replaces an off-topic chart of insurance claims data in the original printing.)

Try It: Control Limit Calculator

Enter the grand mean (x̄̅), average range (R̄), and subgroup size. Constants A₂, D₃, D₄ are looked up automatically.

6.8 Interpreting Control Charts

A process is considered in control when:

A process is out of control when one or more run rules are violated.

6.9 SPC Run Rules (Decision Rules)

Common SPC rules include:

  1. One point outside control limits
  2. Seven consecutive points on one side of the mean
  3. Seven consecutive points increasing or decreasing
  4. Cycles or repeating patterns
  5. Grouping or instability

These patterns indicate special cause variation and require action.

6.10 Relationship Between SPC and Specifications

A process can be:

SPC focuses on process behavior, not pass/fail inspection.

6.11 Chapter Summary — Study Points

Chapter 6 Exercises

Each exercise includes a worked example followed by a student practice problem.

Exercise 1: Identifying Variation Type

Example (Solved)

A process shows small random fluctuations with no patterns.
Conclusion: Common cause variation

Student Practice

A process suddenly shows a large jump after tool replacement. Identify the variation type.

Show answer

Special cause variation — the jump is assignable to an identifiable event (the tool replacement).

Exercise 2: Control Limit Interpretation

Example (Solved)

All points fall within UCL and LCL with no patterns.
Conclusion: Process is in control

Student Practice

One point exceeds the UCL. Determine process status.

Show answer

Process is out of control — one point outside the control limits violates run rule 1.

Exercise 3: X-Bar and R Chart Purpose

Example (Solved)

The X-bar chart monitors changes in the process mean.

Student Practice

What does the R chart monitor?

Show answer

The R chart monitors process variability (the range within each subgroup).

Exercise 4: Specification vs. Control Limits

Example (Solved)

Control limits describe process behavior, not customer requirements.

Student Practice

Explain why a process can be in control but still produce out-of-spec parts.

Show answer

A stable process may be centered incorrectly relative to specifications (or its natural spread may be wider than the tolerance). Control limits come from process data, so a process can behave predictably while making parts the customer cannot accept.

Exercise 5: SPC Action Decision

Example (Solved)

Seven points appear above the center line.
Action: Investigate special cause

Student Practice

A chart shows cycling behavior over time. What action should be taken?

Show answer

Investigate and eliminate the source of the cycling variation — repeating patterns indicate a special cause (for example, temperature cycles or shift changes).

Chapter 6 Self-Check

Answer all three questions, then select "Check my answers."

1. Which statement about control limits is true?
2. Seven consecutive points fall below the center line. What does this indicate?
3. x̄̅ = 0.500, R̄ = 0.010, n = 5 (A₂ = 0.577). What is the X-bar UCL?

Chapter 6 Resources